Get Design Ideas
Find Professionals
Real Homes
Explore Products
For Homeowners
For Professionals
SABARI C
Civil Engineer | Alappuzha, Kerala
Rubble foundation can be completed in 3days 1st day - for setting out earth excavation and leveling 2nd -day foundation dry rubble 3rd -day Random rubble work .. only belt will be pending
1
0
More like this
Rubble Work
after a rainy day disaster, 5 days works
Plinth Beam
Composite plinth beam with rubble work and RCC belt @Kollam . . . . . #Contractor #HouseConstruction #constructionsite #foundation #plastering #CivilEngineer #engineeringย #planning #labour #Residentialprojects #Designs #3d
column footing and columns completed at aroor site
belt leval finished
@Thripunithura Foundation works on progress.. #work #inprogress
Even if the weather is not favorable, we continue to work..Thank God..
#rrmasonary #Rock #perumbavoor #birdsview #foundation #foundations #foundation_prepration
Project @ Edathua
Rubble work.
#blockwork #masonrywork
##leakproof #HouseConstruction #concrete #dreamhouse #plastering #FlooringServices #foundation #Raft beam #column_footing #structuraldesign #reinforcements
Kolo
Kerala
Civil Engineer
SABARI C
1629640809
Join the Community to
start finding Ideas &
Professionals