Sunshade വാര്‍പിനു ശെഷം എത്ര day കഴിഞു ആണു brick work start ചെയ്യുക ?
likes
3
comments
5

Comments


Structure Lab
Structure Lab

Civil Engineer | Kozhikode

10 days

jibin yohannan
jibin yohannan

Contractor | Ernakulam

better cure for 14 days to ensure quality

jibin yohannan
jibin yohannan

Contractor | Ernakulam

min 10 days curing is required for PPC OR PSC

jibin yohannan
jibin yohannan

Contractor | Ernakulam

min 7 days curing is required for OPC

Roy Kurian
Roy Kurian

Civil Engineer | Thiruvananthapuram

curing ചെയ്തതിന് ശേഷം ..atleast 7 days