For how many days should I fill the water for curing on my roof concrete lanter? Some are suggesting me for ~18-20 days but somes are suggesting for as low as 3 days! Kindly advise the way forward! Also please advice minimum days required before open the roof shuttering?
likes
22
comments
16

Comments


Amit Singh
Amit Singh

Civil Engineer | Gurugram

As per IS code min. 7 days of curing is required for concrete to gain around 60-70% of strength. So 7-10 days of curing is enough, excess curing can also be harmful.

RR construction
RR construction

Contractor | Delhi

14 days

The Single Window
The Single Window

Interior Designer | Gurugram

i prefer 15 days to open the lanter.

sandeep kumar
sandeep kumar

Contractor | Gautam Buddh Nagar

7 days only

Naresh Kumar
Naresh Kumar

Home Owner | Sonipat

21 days

7Sky interiors
7Sky interiors

Interior Designer | Gautam Buddh Nagar

5 to 7 days...

SK FABRICATION
SK FABRICATION

Contractor | Delhi

atleast 7 days

Pradeep Srivastava
Pradeep Srivastava

Contractor | Ghaziabad

Minimum 7 Days if you using Curing Compound 7 Days is sufficieant

Skyline Engineers
Skyline Engineers

Contractor | Ghaziabad

at present 10 days sufficient

Syed Shariq
Syed Shariq

Civil Engineer | Delhi

7 days