The construction cost varies from Rs.1600 to 2500/sq.ft. It varies according to design, structure, material used and is also related to the area. Whether it is a town or village area.
Let’s consider an average cost, Rs.1800/sq.ft.
Total cost of building for 900 sq.ft Residential House = 900x1800
= Rs.16,20,000
In this total amount,
Labour cost = 40% of total cost
=40%(16,20,000)
=Rs. 6,48,000
Material cost = 60% of total cost
=Rs. 9,72,000
The material cost can be again subdivided into
1.cement =15% of material cost
=Rs. 1,45,800
2.Reinforcement(load bearing structure)= 17% of material cost
=Rs. 1,65,240
3.Sand = 9% of material cost
= Rs.87,480
4.Aggregate = 7% of material cost
=Rs.68,040
5.Brick(Solid blocks)= 9% of material cost
= Rs.87,480
6.Tile(60/sq.ft) = 8% of material cost
=Rs.77,760
7.paint = 8% of material cost
=Rs.77,760
8.Doors & Windows(wood) = 11% of material cost
= Rs.1,06,920
9.Plumbing & Electrical = 10% of material cost
= Rs.97,200
10.CP & Sanitary Items
= Rs.4% of material cost
=Rs.38,880
10. Miscellaneous (additional electrical,cleaning etc)
= 2% of material cost
=Rs.19,440
Tinu J
Civil Engineer | Ernakulam
The construction cost varies from Rs.1600 to 2500/sq.ft. It varies according to design, structure, material used and is also related to the area. Whether it is a town or village area. Let’s consider an average cost, Rs.1800/sq.ft. Total cost of building for 900 sq.ft Residential House = 900x1800 = Rs.16,20,000 In this total amount, Labour cost = 40% of total cost =40%(16,20,000) =Rs. 6,48,000 Material cost = 60% of total cost =Rs. 9,72,000 The material cost can be again subdivided into 1.cement =15% of material cost =Rs. 1,45,800 2.Reinforcement(load bearing structure)= 17% of material cost =Rs. 1,65,240 3.Sand = 9% of material cost = Rs.87,480 4.Aggregate = 7% of material cost =Rs.68,040 5.Brick(Solid blocks)= 9% of material cost = Rs.87,480 6.Tile(60/sq.ft) = 8% of material cost =Rs.77,760 7.paint = 8% of material cost =Rs.77,760 8.Doors & Windows(wood) = 11% of material cost = Rs.1,06,920 9.Plumbing & Electrical = 10% of material cost = Rs.97,200 10.CP & Sanitary Items = Rs.4% of material cost =Rs.38,880 10. Miscellaneous (additional electrical,cleaning etc) = 2% of material cost =Rs.19,440
Shan Tirur
Civil Engineer | Malappuram
13-15lacks avum
Mohinudeen ka Moideen
Contractor | Palakkad
94953.96238
Vishnudas Puzhakkil
Contractor | Palakkad
call me
NEST BUILDERS AND DESIGNERS
Civil Engineer | Palakkad
15 ലക്ഷം രൂപയിൽ താക്കോൽ കൈമാറ്റം ചെയ്യാൻ കഴിയും. വിളിക്കു
Pushparajan Vadakencherry
Contractor | Palakkad
call.. 996126.1887
Aswin Krishna
Contractor | Palakkad
9xxxxxxxxxx9
rapidhomes kerala
Civil Engineer | Palakkad
Radhakrishnan Radha
Contractor | Palakkad
elevation plan 3D. compression . square feet..1600... total 1440000.. please contact . RK construction. Palakkad stadium stand Mangav..ph.77367.62039..94968.62039
karthik m
Civil Engineer | Palakkad
contact me 98471,93237